WI Highway 16 Project Overview
WisDOT is replacing the pavement on WIS 16 from East Main Street to just 0.23 miles east of the intersection of WIS 16 and Rock River Road (8.85 miles).
Construction: March 17, 2025 – Late fall 2025
Improvements include:
- Replacement of the existing pavement and base material
- Upgrade of guardrail
- Bridge deck surface repairs
- New roundabout at East Main Street & WIS 16
- Mill and overlay at WIS 16 & County F (American St)
Looking for weekly project updates? Email: r.arndt@gremmerassociates.com